Before taking over a restaurant, ask for the records that explain what the kitchen extraction system is, how it has been maintained and what remains unresolved.
The most useful handover file is not a single cleaning certificate. It brings together extract cleaning history, system photographs, fan and mechanical records, design or commissioning information, access limitations, fire-risk actions, insurer requirements and outstanding recommendations.
What records have you received with the restaurant?
Send the latest extract cleaning report or certificate, earlier records, fan service documents, ventilation information and any landlord, insurer or fire-risk correspondence you have. Missing records can be identified before contractors are asked to quote.
Search and Submit Ltd uses your details to respond and coordinate the enquiry, including sharing relevant information with appropriate independent specialists. Read our Privacy Policy. Please omit unrelated personal or sensitive information.
Why do the records matter?
HSE guidance says records of ventilation design criteria, commissioning performance, maintenance requirements, tests and inspections help owners and operators maintain, modify and test a system against its original specification.
That is particularly useful during a takeover. The new operator may be changing the menu, equipment, operating hours or staffing, while the extraction system itself may have been installed for a different type of kitchen.
The handover file should help you understand the system, not just prove that somebody attended the site in the past.
Records to request before completion or opening
Latest extract cleaning report
Ask for the full report showing the system cleaned, photographs, measurements, exclusions, access issues and recommended next action.
Cleaning certificate
Keep the certificate with the report it relates to. The certificate alone may not explain the physical scope or outstanding limitations.
Earlier cleaning history
Previous reports can show whether cleaning intervals, access problems or recurring recommendations have changed over time.
Fan and mechanical service records
Ask separately for fan, motor, drive, control and other mechanical maintenance information. Hygiene cleaning does not replace mechanical servicing.
Design and commissioning records
Where available, these can show the original system intent, airflow or performance information and the operating assumptions used when the system was installed.
Access records
Look for inaccessible ductwork, missing access panels, roof restrictions, high-level access needs and areas previously excluded from inspection or cleaning.
Fire-risk actions
Keep any kitchen extraction recommendation from the premises fire-risk assessment, together with evidence of completed or outstanding work.
Insurance requirements
Ask for relevant policy conditions, risk-survey recommendations or broker correspondence affecting cleaning frequency, contractor status or evidence.
Do not separate the certificate from the report
A certificate may confirm that a particular cleaning activity was completed, but the associated report should explain the physical system, inspection or cleaning scope, photographs, measurements, access limitations and any outstanding work.
If a handover file contains only a certificate, ask whether the accompanying report is available before assuming the whole system was cleaned.
A certificate is useful evidence. It is not a substitute for knowing what was actually inspected or cleaned.
What should the cleaning report tell you?
- Which system was attended. The kitchen and extract route should be identifiable.
- Which components were included. Look for canopy, plenum, ductwork, riser, fan, discharge and other relevant sections.
- What condition was found. Photographs and measurements should relate to identifiable parts of the system.
- What was completed. The report should distinguish completed cleaning from inspection only or other work.
- What could not be accessed. Inaccessible or excluded areas should remain visible.
- What remains outstanding. Access work, repairs, further cleaning or another professional review should be recorded.
- When the system should next be reviewed. Keep the recommendation with the operating conditions it was based on.
Why ask for design and commissioning information?
HSE recommends retaining records of design criteria and commissioning performance because they provide a reference point for maintenance, modification and testing. It also says properly designed and fully specified kitchen ventilation, with recorded design performance characteristics, makes it easier to assess whether the system is appropriate for the load being used.
These records become especially valuable if the new operator plans to add equipment, change the menu or increase production. Without them, the contractor or ventilation professional may have to establish the current system performance from site investigation.
Keep mechanical maintenance separate from extract hygiene
A kitchen extract cleaning report does not establish that the fan motor, bearings, belts, controls or other mechanical components have been properly serviced. Ask for those records separately.
If the fan has a history of weak pull, noise, vibration, intermittent shutdown or repair, keep that history with the takeover file. It may affect opening work even where the extract hygiene evidence is satisfactory.
Access history can be as important as cleaning history
Repeated references to inaccessible ductwork should not be treated as old paperwork. They may identify sections of the system that have never been fully inspected or cleaned.
Check whether later work resolved the access limitation or whether the same exclusion appears across several reports. If the issue remains, roof access, additional panels, high-level access or other enabling work may need to be organised before the next full maintenance visit.
A long history of certificates does not resolve a long history of inaccessible ductwork.
Keep fire-risk and insurance documents with the system records
If the fire-risk assessment, landlord or insurer has raised an extraction action, keep that original wording with the cleaning and maintenance records. This shows why work was commissioned and what evidence may need to be returned.
Do not rely on a verbal summary such as “the insurer wants TR19” or “the fire assessor said it needs cleaning”. The source document is more useful when defining the contractor scope and deciding whether the action has been addressed.
What if there are no records?
Missing records do not prove the system is unsafe, but they also do not prove that it is clean, maintained or suitable for the proposed kitchen operation.
Treat the gap as something to resolve before opening. Depending on the circumstances, that may require competent inspection, extract cleaning, fan or mechanical assessment, ventilation testing, access work or a combination of these.
Historic restaurant project context
Restaurant handovers and openings are easier to manage when the extraction system is treated as a physical route with records attached to identifiable parts of it. Cleaning, fan condition, access and ventilation performance are separate evidence streams that need to be brought together.

Historic EC Cleaners project imagery is used for restaurant context. It is not presented as evidence of the condition, records or maintenance history of another premises.
How to organise the handover file
- Separate records by system. Avoid mixing reports from different kitchens or extract routes.
- Put them in date order. This makes recurring access, cleaning and maintenance issues easier to see.
- Match certificates to reports. Keep each certificate with the evidence package it relates to.
- List missing periods. Record gaps instead of assuming that maintenance occurred.
- Pull out outstanding actions. Access work, repairs, cleaning and professional recommendations should be easy to find.
- Add the new operating plan. Equipment, menu, hours and opening date should sit alongside the inherited system evidence.
- Use the file for contractor briefing. Give the relevant evidence to the specialist before pricing or inspection.
What EC can help organise
Cleaning evidence
Reports, certificates, photographs, measurements, exclusions and recommended return dates.
Ventilation evidence
Design information, commissioning records, airflow information and known performance issues where available.
Maintenance evidence
Fan service records, access history, repairs and outstanding technical recommendations.
Commercial requirements
Landlord, fire-risk, insurer and opening requirements supplied by the customer can be kept with the relevant system records.
EC does not certify the technical adequacy of the inherited system or replace competent mechanical, ventilation, gas, fire-safety or legal advice.
Restaurant takeover records: frequently asked questions
What kitchen extraction records should I ask for when taking over a restaurant?
Ask for the latest extract cleaning report and certificate, earlier cleaning history where available, before-and-after photographs, deposit readings, fan and mechanical service records, design or commissioning information, access records, fire-risk actions, insurer requirements and details of outstanding defects or recommendations.
Is a TR19 certificate enough for a restaurant handover?
No. A certificate can be useful evidence, but it should be read with the report that explains the system scope, cleaning date, photographs, measurements, access limitations, exclusions and outstanding recommendations.
Why should I ask for design or commissioning information?
HSE guidance says records of design criteria, commissioning performance, maintenance requirements, tests and inspections help owners and operators maintain, modify and test ventilation systems against the original specification.
What if no kitchen extraction records are available?
Treat the missing records as an information gap rather than evidence that the system is satisfactory. A competent contractor or ventilation professional may need to establish the current system route, condition, access and performance before the restaurant opens.
Should I ask for fan service records as well as cleaning records?
Yes. Extract hygiene and mechanical maintenance are different workstreams. Cleaning records do not prove that the fan, motor, controls or other mechanical components have been serviced or are operating correctly.
What if the reports show inaccessible ductwork?
Keep the access limitation visible through the handover. The new operator should not assume that a certificate confirms the condition of sections that were not inspected or cleaned.
What should I do with all the records once I receive them?
Organise them by system and date, identify missing periods or conflicting information, note outstanding actions, and use the complete record set when briefing contractors, insurers, landlords or fire-safety professionals.
Do you have kitchen extraction records from a restaurant takeover?
Send the reports, certificates, maintenance records and proposed opening information. EC can help organise the handover evidence, identify obvious gaps and separate cleaning, ventilation, mechanical, access and commercial requirements before the appropriate independent specialists are approached.
Responsibility statement:
EC Cleaners Network is operated by Search and Submit Ltd. Search and Submit Ltd does not inspect, clean, test, survey, design, remediate, certify or technically approve kitchen extraction or ventilation systems. Independent appointed contractors and competent professionals remain responsible for technical assessment, safe working, quotations, physical delivery, reporting, certification and professional conclusions within their appointed scope.
TR19® Grease and TR19® Air are BESA specifications. References are descriptive and no BESA endorsement of or affiliation with EC Cleaners Network is claimed.